With a little manual skill, you can lay a stone carpet yourself – even without prior experience. In this guide, we explain the process step-by-step using the example of a terrace or balcony. The information is taken from our installation instructions, which you can also download as a PDF at the end of this article.
Everything in one package
Our stone carpet complete sets contain primer, quartz sand, binder, marble gravel, and smoothing agent in the correct quantities – simply choose a color and enter the area in m².
What you should know in advance
- Suitable substrates: Concrete, cement and anhydrite screeds, as well as firmly adhering tiles.
- Temperature: Install at a minimum of 5–10 °C to ensure optimal curing of the binder.
- Layer thickness: For marble gravel with 2–4 mm grain size, we recommend approx. 8–10 mm.
- Consumption: Approx. 12.5 kg of marble gravel and 1 liter of binder per m² – a 25 kg bag is sufficient for about 2 m².
- Outdoor use: Plan for waterproofing under the stone carpet and a slope of at least 2%.
- Protective equipment: Wear gloves, safety goggles, and a respiratory mask.
Step 1: Preparing the substrate
Sand the substrate with an angle grinder and a diamond cup wheel and then vacuum up the dust thoroughly. The substrate must be firm, load-bearing, clean, dry, and free of loose particles, oil, and grease. Loose or damaged tiles must be removed or repaired beforehand.
Step 2: Applying the primer
Apply the primer evenly over the entire surface using a paint roller. For outdoor use, we use MARIS Mariseal 710 with a consumption of approx. 200–300 g/m².
Step 3: Waterproofing (outdoor use)
For balconies, terraces, and other weather-exposed areas, we recommend waterproofing beneath the stone carpet. It is applied after the primer and before the stone carpet. We explain in detail which waterproofing you need and how it is applied in the guide Waterproofing stone carpets on balconies & terraces. If no waterproofing is required, this step can be skipped.
Step 4: Scattering quartz sand
Scatter quartz sand (0.4–0.8 mm) evenly – approx. 1 kg/m². The sand creates a non-slip surface and improves the adhesion of the stone carpet.
- Without waterproofing: into the still-fresh primer
- With waterproofing: into the last, still-fresh layer of the waterproofing
Afterward, allow to dry for about 12–24 hours (depending on weather conditions) and thoroughly vacuum up any unbound sand.
Step 5: Installing edge profiles
Edge profiles ensure a clean, stable border, determine the layer height, and protect edges on stairs and terraces. Cut the profiles so that they finish flush everywhere and fasten them at intervals with PU adhesive. This intermittent fastening allows for downward drainage of the stone carpet. Smooth out and remove excess adhesive. You can find suitable profiles under Edge profiles & profile systems.
Step 6: Vertical surfaces first
If you are also covering risers, plinths, or other vertical surfaces, start with these – this ensures no material falls onto already finished horizontal surfaces. For vertical surfaces, use TECHPUR Stone Binder Vertical:
- First, prime the surface with the binder (approx. 300 g/m²).
- Mix marble gravel with approx. 12% binder based on the stone weight.
- Apply the mixture with a trowel – maximum approx. 8 mm so that the material holds securely.
Step 7: Mixing marble gravel and horizontal installation
Mix the marble gravel with the binder (approx. 8% of the stone weight) into a homogeneous mass until all stones are evenly coated. Tip: Since marble gravel is a natural product, mix material from several bags to even out color differences.
First, distribute the mixture evenly to about 10 mm and then compress it with a trowel under light pressure to about 8 mm. Afterward, clean the trowel, spray it lightly with smoothing agent, and perform the final smoothing of the surface – this prevents the stone carpet from sticking to the trowel.
Step 8: Allowing to dry and cure
- after approx. 24 hours: walkable
- after approx. 3 days: furniture can be placed
- after approx. 7 days: fully chemically cured and fully load-bearing
Important: Do not cover the surface with a tarp or other airtight materials during the curing process – air circulation is required for curing.
Optional: Sealing
After complete curing, the stone carpet can be sealed with a pore filler. This makes cleaning easier and is necessary in showers. More on this in the guide Cleaning, maintaining & sealing stone carpets.
Instructions & Video
- Stone carpet instructions for outdoor use (PDF)
- Stone carpet instructions for indoor use (PDF)
- Stone carpet instructions for pool surrounds (PDF)
- Video: Laying stone carpet made easy – step-by-step instructions
For indoor use, the solvent-free binder is used – it is low-odor and intended for interior spaces. You can find the details in the instructions for indoor use.